Search

Newsletter

Failure of Advisor in Drafting a Tender Budget?

A discussion of the judgment of the Arnhem Court of Appeal of 7 April 2009, LJN: BI2152

Introduction
In the Newsletter of May 2009 we have informed you that a bidder who has submitted a too low bid cannot simply escape from being awarded the contract by relying on his abnormally low bid. Submitting a bid is for the account and risk of the bidder; this includes any mistakes the bid may contain. The question is whether the advisor who prepared the tender budget is liable to pay damages to this bidder, as the occasion arises.

The Case
The general partnership Elfbou, a joint venture of two building contractors, has submitted a bid for a construction project in Oldenzaal. Elfbou engaged the services of Nibag, a firm of building consultants to prepare the tender budget. Nibag prepared a tender budget amounting to €1,644,969.95, to be increased by 2% administrative costs and 3% general costs. The total building sum calculated by Nibag amounted to €1,728,204.

In view of the current financial circumstances it was of great importance to Elfbou to secure the contract for the building project. Therefore Elfbou decided not to include the usual margins for profit and risk, and to bid at a price of €1,644,969.95. Elfbou turned out to be the lowest bidder, and was granted the contract. The amount of the bid of number two turned out to be only €65,196 higher than Elfbou's bid.

After having been granted the contract, Elfbou discovered that it could not carry out the work at a cost-effective level. Elfbou took the position that Nibag had made mistakes when preparing the tender budget, as a result of which Elfbou had submitted a too low bid. According to Elfbou, Nibag had failed to include a large number of cost items in its preparation of the tender budget; its calculations with alternative work and materials differed from the specifications; the correct offers had not been requested, or the requested offers had been misinterpreted; and insufficient units and quantities that could be derived from the specifications had been budgeted.
All this constituted an imputable failure on the part of Nibag. Elfbou estimated the loss it had incurred and would still incur as a result of this failure at an amount of €225,680.
Nibag defended itself by arguing that the alleged loss incurred was Elfbou's own doing as Elfbou is a professional party. Nibag was of the view that it was Elfbou's responsibility to check the correctness of the tender budget prepared by Nibag.

In the first instance, the Court of Almelo allowed the claims of Elfbou. Nibag then appealed against this judgment.

The Judgment of the Arnhem Court of Appeal
The Court of Appeal established first and foremost that Elfbou would not have incurred a loss if it had not been the lowest bidder. The difference with the bid of number two is more than €65,000, which is 3.7% of the bid price. If Elfbou would have applied the usual margins for profit and risk, it is likely that its bid would not have been the lowest. The Court of Appeal held that although the decision not to include these margins was Elfbou's own commercial decision, Elfbou had to be able to rely on it that the tender budget prepared by the advisor contained no mistakes that would cause the amount of its bid not to be cost-effective.

On the other hand, the Court of Appeal held that Elfbou could also not simply have assumed that the tender budget prepared by Nibag was correct. Precisely because Elfbou intended to bid at a low price, and to exclude the usual margins for that reason, checking the tender budget was very important. The Court of Appeal also deemed it relevant that after bidding, mistakes cannot be remedied anymore. According to the Court of Appeal, a check is not the same as renewed preparation of the budget, since it is possible to make random checks. The Court of Appeal finds this even more adamant since Elfbou claimed that Nibag had made big mistakes, at least some of which could have been discovered in a random check.

Since Elfbou failed to check the tender budget prepared by Nibag without a valid ground, the Court of Appeal ruled that Nibag was not obliged to compensate the loss incurred by Elfbou. The Court of Appeal deemed it plausible that part of the mistakes for which Nibag was blamed would have been discovered and corrected if a random check had been performed. Taking into account the relatively small difference between Elfbou's bid and that of the number two, the Court of Appeal considered that a correction of only part of the mistakes made by Nibag in the tender budget would have caused Elfbou not to be the lowest bidder. In that case Elfbou would not have incurred a loss.

Consequences for Practice
Nibag's own-fault defense was successful. This judgment of the Arnhem Court of Appeal may have rather drastic consequences for practice. A building contractor who engages an advisor to prepare a tender budget must perform some sort of check of this tender budget. If this check is not performed, the advisor may not be liable to pay damages in the event that the tender budget contains mistakes. It is not necessary to redo the entire calculation; a limited check may suffice. I also like to add the comment that in this particular case Elfbou deliberately left out the margins for profit and risk, so that in the opinion of the Court of Appeal its interest in a correct tender budget was even greater.

Share this:   
linkedin facebook twitter email
Hilleke Hollenbeek Brouwer

Tel: +31 20 5506 647
E-mail: hilleke.hollenbeek.brouwer@kvdl.nl

View our profile

linkedin