Search

Newsletter

Obligation to Award After the Notification of a Preliminary Award Decision?

A discussion of the judgment of the Court of The Hague in Preliminary Relief Proceedings dated 4 August 2008 (LJN: BD9379).


The key question in these proceedings is whether the municipality of The Hague has the right to withdraw the procurement procedure after having notified the bidders of its award decision.

The Facts

The municipality of The Hague organized a European procurement procedure. The contract concerned the supply of approximately eight million red paving bricks in and around the municipality of The Hague. The supply would take place on call and in partial deliveries during a period of one year, with the possibility to extend this period twice with one year. The award criterion was the lowest price.

The procurement procedure took place on 29 April 2008. On this date five parties supplied a specimen, after which two potential bidders dropped out. Following this the three selected bidders submitted a bid. The lowest bidder was De Bylandt.

In a letter dated 26 May 2008 the municipality informed De Bylandt of its intention to award it the contract. One of the other bidders objected against this award decision by instituting preliminary relief proceedings.

A couple of weeks later, on 20 June 2008, the municipality informed De Bylandt in writing that it would not carry out its intention to award the contract to De Bylandt. The reason for breaking off the procurement procedure was the administrative decision of the municipality of The Hague to suspend the new organization structure for the purchase of materials - which would be carried out centrally from then on - for an indefinite period of time. According to the municipality, as a result of this decision the starting points of the procurement procedure were cancelled. This was the reason why the municipality would not give the contract. In this letter the municipality already announced that it would once again invite bids for the modified contract.

De Bylandt objected against this decision of the municipality and claimed in preliminary relief proceedings, in summary, that the municipality be ordered to execute its intention to award the contract to De Bylandt and be prohibited from proceeding to re-invite bids for the contract. In this respect De Bylandt took the position that it had not been proven that the contract could not be awarded in a legally valid manner. No irregularities had come to light in the procedure, and the suspension of the organization structure by the municipality of the Hague would not lead to a material change in the specifications of the contract either.

Court of The Hague in Preliminary Relief Proceedings

The Court first and foremost held that in principle a contracting authority is free to break off a current procurement procedure and to initiate a new procurement procedure. Subsequently, the Court commented that this might be different if the procurement procedure has reached the awarding phase. In that case the contracting authority would have taken note of the bids, as a result of which the principle of equality and the principle of legitimate expectations as well as the precontractual good faith could stand in the way of a re-inviting of bids. According to the Court this is the case if one or more suitable offers have been made and there is no question of a material change in the specifications of the contract in the intended re-inviting of bids.

The Court considered that the municipality of The Hague has not made it plausible that the suspension of the new organization structure must lead to a material change in the specifications of the contract. According to the Court, the total need for red bricks of the municipality of The Hague remains unchanged, just like the technical requirements that are set on bricks. The consequences of the suspension of the new structure for the actual performance of the contract are relatively limited. For these reasons the Court ruled that the municipality of The Hague has reconsidered its intention to award on incorrect grounds.

Comments

In this judgment the Court wrongfully involved the question of whether in the event of a possible re-inviting of bids there is a material change of the contract. Thus, the Court ignored that a contracting authority is free at all times to break off a procurement procedure, irrespective of the stage that the procedure has reached. There is no question of an obligation to award, not even if the procurement procedure has reached the final stage and the contracting authority has announced its intention to award to the bidders. This follows from the principle of contractual freedom and is established case law of the European Court of Justice.

However, a contracting authority is obliged to communicate the reasons for its decision to withdraw the procurement procedure. The grounds for the decision must allow the bidders to verify whether the contracting authority has not violated any general principles of procurement law with this decision. Actually, this means that the grounds for the decision of the contracting authority must be sufficient to allow the bidders to assess whether the assumptions on which the decision not to proceed to award is based are defensible.

The question of whether there is a material change of the contract is not relevant at this stage. This question will only be discussed if the municipality of The Hague actually decides to re-invite bids for the contract. The original contract may not be marketed once again just like that; there must be a material change in the specifications of the contract.

Share this:   
linkedin facebook twitter email
Hilleke Hollenbeek Brouwer

Tel: +31 20 5506 647
E-mail: hilleke.hollenbeek@kvdl.nl

View our profile

linkedin